As I explained in the last post ...
I had the pleasure of working with a really great team recently - a team that were dealing with a very dynamic situation - a new team that never met each other before the project started - a team that were working on a very challenging project.
Overall Project's Process
We worked together to develop this simple but practical process for each Team Member for step 4 of the Project's approach (which is copied here again).
- [Friday] Project planning and re-planning
- [Saturday] Communication of the latest plan to the team (via an automated email from pmPoint)
- [Everyday!] Everyone does lots of work and the team makes great progress
- [Late Wednesday] Everyone makes a personal progress update on tasks and issues
- [Thursday at 2pm] Weekly Team Meeting with the following agenda:
- Review, discuss and resolve (in so far as possible) issues
- Look at upcoming tasks for next week
- (time permitting) Look at tasks achieved last week or the highlight tasks
Team Member Update Process
- Update My Tasks for the past week by updating values in the simple grid
- Perhaps change the status field to say "In Progress" or "Completed"
- If you have started a task, then enter the "Actual Start Date"
- If you have completed a task, then enter the "Actual Finish Date"
- If the task in question is problematic you may select the "Issue Indicator" field and provide details in the "Issue Description" fields
- Also feel free to add comments and other details in the "Description field"
- Optionally:
- Check your work for the coming week - My Work Due Soon or My Gantt
- This is in as an optional task as you will be getting an email reminder about your upcoming work!
- Add a project document to the Documents folder
- Add non-critical project To Dos
- Check the overall status of the project by looking at the Weekly Status Report